701 CATHEDRAL RD, Philadelphia, PA 19128
Addition in Philadelphia, Pennsylvania
| Type | Addition |
|---|---|
| Category | Commercial |
| Scope | FOR PARTIAL DEMOLITION, ERECTION OF AN ADDTITION, OVERHANGS, CANOPIES, AND FOR LEVEL II ALTERATIONS TO INCLUDE NEW PARTITIONS, FIXTURES FURNISHINGS, FINISHES AS PER APPROVED PLANS. BUILDING TO BE SPRINKLERED PER NFPA 13. SEPARATE PERMITS REQUIRED FOR MEP AND FIRE SUPPRESSION WORK. *2018 IEBC* *ASBESTOS ABATEMENT REQUIRED PRIOR TO START OF WORK.* AMENDMENT 6/6/25 TO INCLUDE STRUCTURAL CHANGES, DOCUMENT IN FEILD CONDITIONS/CHANGES, EXTERIOR WALL OPENING/STOREFRONT MODIFICATIONS. AMENDMENT 7/29/25 TO INCLUDE THE ERECTION OF NEW CMU WALL. |
| Status | Issued |
| Est. timeline | 2025-02-03 → ? |
| Registered | 2025-02-03 |
| Construction started | 🚧 2025-02-03 |
| Address | 701 CATHEDRAL RD, Philadelphia, PA 19128 |
| Owner | ANDORRA ASSOCIATES |
| Contractor | NATIONAL MAINT & BUILD OUT LLC |
| Permit | PHL-CP-2024-005841 |